Home / Camber inspection plan for an overhead crane main girder
DOWNLOADABLE MEASUREMENT PLAN

Camber inspection plan for an overhead crane main girder

For no-load camber of an overhead crane main girder (22.5 m span, example/teaching data) with a loaded-deflection comparison. With the support and trolley position fixed, the autocollimator profiles the centreline of the top cover plate; camber is evaluated against the endpoint line and re-measured under load for comparison.

Instruments

Procedure

Calculation

Camber f=max(hi−(h0+i·(hn−h0)/n)); with L=250 mm, 1″≈1.212 μm (example/teaching data). Segments are spliced by least-squares registration of the overlap; loaded deflection is the difference between loaded and no-load profiles.

Reporting

Limitations

Does not replace the rated-load stiffness test or lifting safety assessment; under strong solar gradients the data serve as trend reference only. Girder fatigue and weld condition are outside this plan.

STEP BY STEP

Understand the measurement step by step

  1. 01

    Confirm the 22.5 m span (example), no-load support state and trolley position, and the endpoint-line evaluation agreement.

  2. 02

    Lay out stations on the top cover plate centreline at a 250 mm span using equal-span pads.

  3. 03

    Read the autocollimator interval by interval to 0.1″; measure the full span in segments with splice registration.

  4. 04

    Integrate via Δh=L·tanθ, subtract the endpoint line; the maximum residual is the camber.

  5. 05

    Reverse-repeat and log ambient temperature and solar exposure.

  6. 06

    Re-measure the same line under test load (0.5× rated, example) for the deflection comparison.

  7. 07

    Deliver no-load/loaded profiles, camber value, environment log and the repeat comparison.

Principle schematic · not to scale
1 / 5
  1. Model support · Girder model supported at the scaled span.
  2. End station · Autocollimator set at the bridge end.
  3. Profile steps · The 200 mm bridge scans the top flange.
  4. Log pitch · Pitch readings recorded per segment.
  5. Profile evaluation · Cumulative conversion yields the camber line.

Teaching animation: follow the stations and reference directions. Do not read dimensions or angles from the schematic.

WORKED EXAMPLE

Overhead Crane Girder Camber Inspection · Tutorial Case

Teaching example with assumed data, not a customer project, instrument accuracy claim or acceptance result.

Example task

Teaching demonstration, not a real customer project: segmented local profile survey of an overhead crane girder camber on a teaching model; data are instructional settings.

Setup and preparation

  • Support the girder model at the scaled span on the rig

  • Place the autocollimator at the bridge end with the optical axis along the top flange

  • Move a 200 mm bridge along the top flange step by step

  • Record the pitch reading per segment

  • Cumulate and convert for the camber profile

Example data and records

  • Bridge span L=200 mm; segment 1 autocollimator reading θ₁=+0.8″

  • Segment 2 autocollimator reading θ₂=+0.4″

  • Segment 3 autocollimator reading θ₃=-0.2″

Calculation steps

Height conversion: Δh = L·tan(θ·π/648000)×1000 (μm). Segment 1: 200×tan(+0.8″)=+0.78 μm; Segment 2: 200×tan(+0.4″)=+0.39 μm; Segment 3: 200×tan(-0.2″)=-0.19 μm. Cumulative heights: 0→+0.78→+1.17→+0.98 μm; peak-to-valley PV=+1.17−(+0.00)=+1.17 μm.

Interpretation

Tutorial result PV≈1.17 μm, demonstrating micrometre-level segmented profiling of the girder camber.

Verification and pitfalls

  • Support positions mimic the real span bearings

  • Bridge avoids weld zones on the flange

  • Model undisturbed during readings